Failure Analysis of A 304 SS Girdling Loop of the Boiler in a 500 MW Thermal Power Plant

Gnanamoorthy, J B and Jayakumar, T and Raj, Baldev (1995) Failure Analysis of A 304 SS Girdling Loop of the Boiler in a 500 MW Thermal Power Plant. In: Proceedings of the National Workshop on Boiler Corrosion (NWBC-95), April 11-12, 1995, NML, Jamshedpur.

[img]PDF
2967Kb

Abstract

There were many cases of girdling loop failures in the reheater section of the 500 MW boilers of athermal power station after being in service relatively for a short period of a few months. Within seven months of synchron-ization, the bottom 'U'portion of the front reheater girdling loop of the boiler of 500 MW thermal power plant had developed a leak. The plant was restarted alter replacing the failed protion of the type 304 stain-less steel 'U' tube. Failure occurred again within seven months of operation. Similar failures followed in the other units of the station.

Item Type:Conference or Workshop Item (Paper)
Official URL/DOI:http://eprints.nmlindia.org/3560
Uncontrolled Keywords:Synchronization, Stereomicroscopic, Reheater section
Divisions:Corrosion and Surface Engineering
ID Code:3560
Deposited By:Sahu A K
Deposited On:21 Jul 2011 11:59
Last Modified:02 Dec 2011 12:30
Related URLs:

Repository Staff Only: item control page